Plants / Water Treatment Unit / Operator training

Operator training

A training simulator on the plant's own drawing. Click pumps to start or stop them, and control valves to set them. One second here is one minute in the plant.

Sheet
1 1 2 2 3 3 4 4 5 5 6 6 7 7 8 8 A A B B C C D D E E F F NOTES 1. Backwash a filter when its pressure drop passes 0.8 bar, or every 48 hours. 2. Backwash valves XV-3206 and XV-3207 are run by the filter sequence in the control system. 3. Filter 2 backwash piping is the same as filter 1, not shown. INSTRUMENT SYMBOLS Field mounted Control system (DCS), operator can see it Electric signal Main process line Utility / secondary line ENTHRA LABS DEMO DRAWING WATER TREATMENT UNIT PIPING AND INSTRUMENT DIAGRAM: SAND FILTRATION DRAWING NO. PID-3201 SHEET / REV 2 OF 4 REV 0 SCALE: NONE DATE: 2026-11-24 FICTIONAL PLANT FOR DEMONSTRATION. NOT FOR CONSTRUCTION. SF-3201 SAND FILTER 1 SF-3202 SAND FILTER 2 TK-3201 FILTERED WATER TANK P-3201 BACKWASH PUMP PID-3101 FROM CL-3101 14"-RW-3106-C10 PID-3101 FROM CL-3101 14"-RW-3201-C10 FV-3202 10"-TW-3202-C10 FV-3203 10"-TW-3203-C10 PID-3301 TO UV-3301 14"-TW-3204-C10 10"-TW-3205-C10 S XV-3206 10"-TW-3206-C10 B/L BACKWASH DRAIN S XV-3207 10"-WW-3207-C10 PDT 3201 0-1.5 bar PDI 3201 PDT 3202 0-1.5 bar PDI 3202 FT 3202 FIC 3202 FT 3203 FIC 3203 LT 3201 LIC 3201 AT 3204 0-2 NTU
50%50%50%100%100%100%100%

Feed into SF-3201 jumps 50% two minutes in. Keep the level between 15% and 85% for 30 minutes.

0 / 30 min
Click a pump to start or stop it. Click a valve (yellow) to set how far open it is.
Alarms
None
0m Started: Feed upset

Training records

No runs yet.