Safety Studio

Prepares the HAZOP from the drawings and checks the relief valves. It saves prep time; the team still runs the review and signs off every row. Legal responsibility for safety stays with the plant.

HAZOP ExcelCSV
TK-2001 peroxide storage tank a
PID-2001 · design temp 40 C · design pressure ATM · feed about 5 m3/h (quick simulation)
No flowDraft
Causes
  • P-2003 stops
  • Hand valve on the inlet left closed
Consequences
  • Downstream of TK-2001 runs short of feed
  • Pumps further on can run dry
  • Quick simulation, P-2003 stopped: 40 lines change flow
Safeguards
  • Level indication LT-2001, LAH-2001
Action
None
More flowDraft
Causes
  • Upstream pump running faster than normal
Consequences
  • TK-2001 overfills
  • Downstream equipment overloaded
Safeguards
  • Level control LT-2001, LAH-2001
Action
None
Reverse flowDraft
Causes
  • P-2003 stops while TK-2001 is under pressure
Consequences
  • Back-flow from TK-2001 through the stopped pump
Safeguards
  • Check valve on the pump discharge
Action
None
High levelDraft
Causes
  • HV-200103 left closed
  • Outlet pump stops
Consequences
  • TK-2001 overflows or liquid goes into the vent
  • Spill of hydrogen peroxide 50 wt%
Safeguards
  • Level LT-2001, LAH-2001
  • Relief PSV-2001
Action
None
Low levelDraft
Causes
  • Feed stops
Consequences
  • Outlet pump runs dry and is damaged
Safeguards
  • Level LT-2001, LAH-2001
Action
None
High pressureDraft
Causes
  • Outlet blocked (valve closed)
  • External fire
Consequences
  • TK-2001 pressure rises
Safeguards
  • Relief PSV-2001 set 0.05 barg
Action
None